A neighbourhood café, refitted without closing
← Projects
Nunhead · Commercial · November 2025

A neighbourhood café, refitted without closing

A café that closes for a month often doesn't reopen. So the programme was the design brief.

We split the job into three phases: the back-of-house kitchen and extract over two weekends, the counter and services over four nights, and the front and decoration in the final week with a temporary counter serving from the door.

The counter is oak and painted timber, made in our workshop and fitted in one night. Under it are the fridges, the pass and enough electrical capacity for the espresso machine the owners are saving up for.

The front is a pair of timber-framed folding doors painted the same navy as the fascia, with the sign painted by hand. On a warm day the whole front disappears.

Programme · 4 weeks
Kitchen and extract (weekends)1 week
Counter and services (nights)1 week
Front and decoration1 week
Signage and snagging1 week
Where the money went · £58k
Kitchen and extraction£18k · 31%
Counter and joinery£13k · 22%
Electrics and plumbing£10k · 17%
Shopfront and signage£11k · 19%
Flooring and decoration£6k · 11%
Milestones · 4 weeks on site
  1. Week 0Call, survey and fixed priceDrawings agreed, price fixed before anyone starts
  2. Week 1Kitchen and extract (weekends)1 week on site
  3. Week 2Counter and services (nights)1 week on site
  4. Week 3Front and decoration1 week on site
  5. Week 4Signage and snagging1 week on site
  6. Week 4HandoverClean, paperwork handed over, keys back
  7. Week 10Snagging visitWe come back and put right anything on the list
Before and after
Drag to compare
After: A neighbourhood café, refitted without closing
Before: A neighbourhood café, refitted without closing
⇔
BeforeAfter
Walkthrough
The new front: timber folding doors painted to match the fascia, sign painted by hand.
01The new front: timber folding doors painted to match the fascia, sign painted by hand.
02Counter in oak and painted timber, fitted in a single night.
03Extract run concealed in a boxed bulkhead that also carries the lighting.
Back-of-house shelving built from the same boards as the front.
04Back-of-house shelving built from the same boards as the front.
“They worked nights for the last fortnight so we never closed. Takings went up the week we reopened.”
Marc · the owner
What we'd tell you before starting one of these

Ask how the work will be phased before you ask what it costs. A cheaper quote that closes you for six weeks is not cheaper.